CERC Allows Chhattisgarh Discom to Amend ₹85 Crore Safeguard Duty Claim Against Adani Solar
The Central Electricity Regulatory Commission has allowed Chhattisgarh's power discom to amend its petition seeking an 85 crore rupee safeguard duty refund from Adani Solar over a 450-megawatt hybrid project.

In this piece
The Central Electricity Regulatory Commission has permitted Chhattisgarh State Power Distribution Company Limited to amend its 85.28 crore rupee claim against…
The Central Electricity Regulatory Commission has granted permission to Chhattisgarh State Power Distribution Company Limited to amend its petition regarding an 85.28 crore rupee safeguard duty dispute against Adani Solar Energy Jaisalmer One Private Limited. The power regulator rejected objections raised by the renewable energy developer, allowing the state distribution utility to formally incorporate foundational customs notifications into its claim. The ruling paves the way for a substantive hearing on whether the discom is entitled to compensation or tariff adjustments under change-in-law provisions.
In its procedural application, the Chhattisgarh discom sought to revise its original filing to explicitly reference a central government customs notification issued on July 30, 2018, alongside a subsequent 2020 notification. The utility argued that citing the foundational notification was essential to properly articulate its change-in-law claim regarding safeguard duty variations on imported solar equipment. The commission agreed, characterizing the proposed amendment as purely clarificatory and integral to adjudicating the underlying controversy.
The dispute stems from a power procurement arrangement involving a 450-megawatt wind-solar hybrid project developed by Adani Solar in Rajasthan. The Chhattisgarh distribution company purchases electricity generated from the hybrid facility through the Solar Energy Corporation of India, which acts as the intermediary nodal agency. Under the power sale agreements, tariff adjustments and financial reconciliations can be triggered if legislative or regulatory actions alter project capital costs after contract execution.
CSPDCL filed the initial petition seeking financial relief of approximately 85.28 crore rupees, asserting that duty cuts on imported solar cells lowered the capital expenditure incurred by the developer. The state discom argued that the reduction and ultimate expiry of safeguard duties constituted a negative change in law that worked in the developer's favor. As a result, the distribution utility maintained that the financial benefit should be passed down through a downward tariff revision or a lump-sum compensation with carrying costs.
Adani Solar strongly resisted the discom's amendment request, urging the commission to dismiss the procedural plea. The developer contended that the amendment sought to introduce fresh legal grounds well past statutory limitation deadlines. Furthermore, the company argued that Chhattisgarh's financial calculations were based on speculative assumptions rather than empirical procurement records reflecting actual solar module imports and customs payments.
In its order, the central power regulator dismissed Adani Solar's arguments, labeling the procedural objections hyper-technical. The regulatory bench observed that correcting statutory references did not alter the fundamental character, financial quantum, or relief claimed in the original petition. The commission emphasized that procedural rules exist to advance justice rather than trap litigants, noting that allowing the amendment would cause no prejudice to the project developer.
The dispute underscores an increasingly contentious regulatory arena in India's renewable energy sector regarding negative change-in-law claims. While power developers routinely seek tariff hikes when duties and taxes increase, state-owned distribution utilities have become equally vigilant in claiming clawbacks when tax rates decrease. For cash-strapped state distribution companies, reclaiming such cost reductions is critical to managing overall procurement expenses and retail tariffs.
Industry observers note that scrutiny over module procurement and duty reconciliation has intensified across several inter-state solar and hybrid projects. Regulatory determinations requiring detailed customs documentation and import timelines are now standard practice in such litigations. If discoms successfully demonstrate cost savings, developers may be required to return substantial sums or accept adjusted tariffs over long-term power purchase agreements.
With the amendment formally approved, the Central Electricity Regulatory Commission is set to proceed with hearings on the merits of the Chhattisgarh discom's petition. Adani Solar will have the opportunity to submit its detailed rebuttal on whether the safeguard duty notifications resulted in quantifiable cost savings for the 450-megawatt hybrid facility. The forthcoming verdict will offer greater legal clarity on the evidentiary thresholds required for state utilities to recover safeguard duty benefits under federal renewable energy contracts.