The Union Environment Ministry's Forest Advisory Committee has constituted a three-member panel to evaluate the ecological and socio-economic fallout of the proposed 1,720-megawatt Kamala hydroelectric project in Arunachal Pradesh.

In this piece
The Union Environment Ministry has appointed an expert panel to examine the environmental and socio-economic impacts of Arunachal Pradesh's proposed 1,720 MW…
The Union Ministry of Environment, Forest and Climate Change has constituted a three-member sub-committee to assess the ecological and socio-economic impacts of the proposed 1,720-megawatt Kamala Hydroelectric Project in Arunachal Pradesh. The panel was formed under the ministry's Forest Advisory Committee following deliberations over the vast scale of forest diversion sought for the multi-crore infrastructure venture. Members will scrutinize whether the project design adequately accounts for the preservation of fragile Himalayan ecosystems.
The inspection sub-committee is headed by Forest Advisory Committee member M.M. Pant, alongside committee member Nityanand Srivastava and scientist Charan Jeet Singh. The team has been tasked with conducting an on-ground review of the site and evaluating the detailed documentation submitted for statutory forest clearance. Their evaluation will directly inform the advisory body's eventual appraisal of the state utility proposal.
Planned along the Kamala River, a significant right-bank tributary of the Subansiri River, the massive project is slated to be developed by state-run hydropower major NHPC Limited. Estimated at an investment of over 26,000 crore rupees, the facility is designed to augment India's renewable energy capacity and provide grid stability. However, the sheer engineering scale of the undertaking has made regulatory scrutiny particularly rigorous.
Executing the ambitious project requires the diversion of approximately 3,278 hectares of dense forest land spread across the Kamle, Kra Daadi, and Kurung Kumey districts of Arunachal Pradesh. The project footprint encompasses heavily forested catchment zones that sustain diverse indigenous flora and fauna in the Eastern Himalayas. Officials must determine how much of this pristine terrain can be preserved through engineering adjustments.
Environmental groups and regulatory authorities have raised serious concerns over the ecological toll of the undertaking, which entails felling an estimated 23.4 lakh trees and bamboo clumps. Official project records indicate that a substantial portion of the prospective clearing falls within designated High Conservation Value areas. Such extensive deforestation threatens critical wildlife habitats, soil stability, and local ecological connectivity.
In light of these ecological risks, the sub-committee has been mandated to examine whether the project's forest land requirement can be meaningfully curtailed. The panel will explore technical options to minimize the overall reservoir submergence zone and limit the clearance of contiguous green cover. Experts will assess whether dam structural modifications can reduce environmental damage without compromising power generation capacity.
Beyond environmental degradation, the expert committee will examine the project's human toll, particularly the socio-economic repercussions on local indigenous populations. Initial assessments show that approximately 1,300 families across multiple tribal villages face displacement or severe loss of agrarian livelihood due to land acquisition and reservoir inundation. The panel will gauge how deeply river-dependent traditions and settlements might be disrupted.
The team will critically evaluate the adequacy of the rehabilitation and resettlement packages formulated for the project-affected communities. Striking an equitable balance between clean energy infrastructure and indigenous rights remains a contentious challenge across river basin planning in the frontier state. The sub-committee will verify whether institutional support mechanisms provide sufficient compensation and alternative livelihoods.
The sub-committee is expected to submit its findings and actionable recommendations to the Forest Advisory Committee following its site inspection and consultations with stakeholders. The central statutory body will subsequently determine whether to recommend forest clearance, mandate comprehensive design alterations, or impose binding environmental safeguards. Its conclusions will serve as a crucial benchmark for future mega-hydel development throughout the region.